Voters will be asked to decide tonight – 6 p.m. Tuesday, Dec. 16 – whether to allow Town expenditure of up to $750,000 more than originally planned for renovation of Town Hall. The funds would come from the town’s existing undesignated fund and would not be raised by additional taxes.

The cost of renovating the 99-year-old building, originally set at $7.35 million, has increased by some $382,000. The overrun is due to increased material costs, a delay in getting started and tariffs imposed this year, Town Manager Tim Pellerin said earlier this fall.

The Town Council will present its request and explain the funding at a special town meeting at 6 p.m. in the Town Hall auditorium, and residents will be invited to ask questions or make comments before the vote is taken, according to Councilor Mallory Cook.

In a public hearing before the Dec. 9 council meeting, five residents stated concerns about using up to $750,000 from the undesignated fund for additional potential shortfalls, though they all expressed support for renovating Town Hall.

“What can we do to get a building as close as possible to what we wanted, but now that we know the costs, we gotta cut back, just like our families do,” asked Paul Steinhauer of Hill Drive. Tamre Steinhauer, also of Hill Drive, asked for more clarity about project priorities. 

“I found it very difficult to find a list of the must-haves versus the nice-to-haves,” Tamre Steinhauer said. “There needs to be a really clear list, an ABC: ‘this is what we really want and this is what we really need’.” 

Former town councilor Melissa Costella of Boyd’s Corner Road said she recognizes that the town wants to deliver on its promises for the project, but questioned whether some aspects of the plan could be scaled back, in particular the number and upgrades of bathrooms.

During the more than hourlong public hearing, the speakers supported paying for critical items like heating systems, windows, the elevator and a better sound system for the auditorium, but questioned some of the other expenses. 

During renovations, certain upgrades are required to meet updated building codes, including for bathrooms, according to Cook. The request is for “up to $750,000,” she noted, adding that completion of the project as planned may cost less than that.

Residents voted overwhelmingly in 2024 to renovate Town Hall rather than build something new, wanting to retain the flavor and feel of the town, council Chair John James pointed out.  

The amount being requested of voters at the special town meeting can be reduced but not increased. If the request is voted down, the process would have to begin anew, said James. 

The council, which has approval authority over any expenditures, will control whether and where the $750,000 is spent, he said, and money not needed for the renovation would remain in the undesignated fund.

Councilor Sam Flinkstrom suggested that having a “quick reference sheet..(of) the exclusions in the Charters Brothers contract .. that could potentially require use of these funds, would be super valuable to everyone.”

The Town in May took out a $6 million bond for the renovation project, money that is now in an interest-earning account.

According to Finance Director Jennifer Janelle, the undesignated fund now totals $8.4 million; the town is required to keep about $3.9 million in the fund. The remaining $4.3 million includes the $1.35 million earmarked for work on the Town Hall. 

Project manager Michael Bean of Charters Brothers Construction, the project contractor, told the council that delays mean risking the loss of contractors who have bid on the project, as well as shortening supply chain lead times, and missing deadlines for jobs bid in 2025.